INSTALLATIONS PLANNED TO A T

JRC Machinery’s technical team has installed hundreds of CNC machines over the years. Furthermore, our automation team offers full training so your CNC machinery operators will have you up and running in no time.

We distribute many of the industry’s leading brands, which require precise knowledge when it comes to installation time. In the weeks leading up to the installation of your machinery, the manager assigned to your project will carefully go over the installation and training process to ensure all key points are covered.

The following steps are what typically goes into the installation of our machinery.

EXAMPLE OF AN INSTALLATION AND TRAINING PROCEDURE

DAY 1
  • Upgrade the machine
  • Removal of transportation brackets
  • Electrical check at machine input and insertion of fuses
  • Connection to internet and verification of remote communications
  • Reset of axes
  • Calibration of machine parts and tooling
DAY 2
  • Presentation of the machine
  • Operator safety
  • Machine parts
  • Tool change
  • Indexing and location of hardware
  • Clamping of profiles
  • Presentation of production page
DAY 3 & 4
  • Manual production
  • Presentation of most common operator errors
  • Machine alarms
  • Remote PLC and HMI access
  • Automated production
DAY 5
  • Creation of users
  • Explanation of service request process
  • Machine maintenance
  • Perform data backup